On the fuel storage secondary containment EC Applications lined for Hawaiian Electric Company, the liner covered three surfaces: the containment walls, the floor, and the tank ring wall. The material was 45 mil XR-5 over a 12 ounce geotextile, held with stainless steel mechanical attachment. That list of surfaces is the whole story of tank containment work. The open floor is simple. Every place the liner stops is not.
Lining around tanks is a different job from lining an empty pond. The tanks stay where they are, the piping stays connected, and the facility usually keeps running. This post walks through what changes when the containment has to be lined around equipment that is not going anywhere.
Why owners line containment that already exists
Most tank containment starts as a concrete dike or an earthen berm. Concrete cracks at joints and around anchor bolts, and compacted soil is rarely tight enough by itself. For oil and fuel, the federal SPCC rule (40 CFR Part 112) applies once aboveground storage passes 1,320 gallons and calls for containment that is sufficiently impervious to hold a discharge until it is cleaned up. A geomembrane installed over the existing structure is the usual way to get there without demolishing the dike or emptying the tanks.
The same need turns up across the markets we serve. Mines keep diesel, reagent, and process tanks inside containment. Landfills store fuel for the equipment fleet, and many keep leachate in tanks. Water and wastewater plants store treatment chemicals. In each case the tanks are part of daily operations, and the containment gets lined around them.
The liner cannot go under an existing tank
In an empty pond the liner is one continuous sheet. In a tank containment, every tank footprint interrupts it. An existing tank sits on its ring wall or foundation, and lifting it to slide a sheet underneath is almost never practical. So the liner runs up to the foundation and terminates there, and that termination becomes part of the containment boundary.
A ring wall termination is a batten bar or similar mechanical attachment fastened into sound concrete, with a compatible sealant behind the sheet so liquid cannot track under the edge. The same detail repeats along the top of every containment wall. Stainless steel hardware is the common choice outdoors and around fuel, because the attachment has to last as long as the membrane it holds. The HECO record lists the tank ring wall as a lined surface in its own right, next to the walls and floor, which is how these jobs should be scoped.
Sealing around piping that stays connected
Pipes, pipe supports, ladders, grounding rods, and pump skids all pass through or stand on the containment floor. On new construction a crew can slide a prefabricated boot over an open pipe end. Around live piping there is no open end. The boot is fabricated with a split, wrapped around the pipe in place, and welded closed along the split. Then it is welded to the floor sheet and clamped to the pipe with stainless steel bands over sealant.
Each boot is a small fabrication job done by hand in a tight space, and each one is a place a leak would start if it were done poorly. In tank containment, the penetration count usually drives the schedule more than the square footage does.
Hot work beside stored fuel
Geomembrane seams are heat welded. Hot wedge, hot air, and extrusion welders all count as hot work, and a facility that stores fuel will typically require a hot work permit, atmospheric monitoring, and a fire watch before any welder is switched on. Some areas may be closed entirely while a tank is filling or a line is open.
Two things cut that exposure down. The first is shop fabrication. The crew measures every wall, corner, tank, and penetration, and the floor and wall sections are welded into large panels in the shop, where EC Applications fabricates panels up to 25,000 square feet. The second is sequencing, so the field welding that remains fits the windows operations can give. Less welding next to the tanks means a shorter permit window.
Matching the liner to what the tanks hold
The liner has to tolerate whatever it may someday contain, plus years of sun while it waits. For fuel service, XR-5 is a common specification because its manufacturer publishes compatibility data for fuels including diesel and jet fuel, and its polyester scrim holds dimension at walls and terminations. On the HECO containment the 12 ounce geotextile went under the XR-5 as a cushion against rough concrete and the edges of the existing structure.
For reagents, leachate, or treatment chemicals, the answer may be a different material. Check the specific liquid, concentration, and temperature against the current chemical resistance chart during submittal review, not after the liner is down.
Proving the containment before it goes back into service
Field seams are tested as they are made. Dual-track wedge welds are air pressure tested through the channel between the two tracks. Extrusion welds and boots are vacuum box tested. Results are recorded by location, so the owner has a record for the facility inspection file.
Two operating details belong in the design too. Rain collects in a lined containment, so the drain valve and sump need a sealed detail and a procedure for checking the water before it is released. And an exposed floor sheet with little on top of it can lift in wind, so ballast or attachment gets planned up front rather than after the first storm.
Where the difficulty actually is
The open floor of a tank containment is the easy part. Whether the containment holds is decided at the ring walls, the wall tops, the split boots, and the welds made under a hot work permit next to stored fuel. That work favors a crew that has done those details many times. Our crews are the most experienced in the industry. They consistently deliver high quality installations with unparalleled customer service.
EC Applications fabricates and installs drop-in and field-installed secondary containment liners from offices in Anaheim, California, Midland, Texas, and Sparks, Nevada, under California contractor licenses CSLB #894068 and CSLB #1003207.